This is a site to record our adventures aboard Owl Moon.

Wednesday, August 31, 2016

No more leaking keel bolts!

August 25, 2016  I wasn't able to be present for the launch, but the in the water test was successful...no leak in the bilge.  The bad news is that they found that the air conditioner thru-hull valve has a very slow leak.  Not a big problem as it is accessible and they only planned on leaving the boat in the water long enough to test all the work that was done that required the boat being in the water to test.  Everything else checked out.  They reported what I already knew...that some of the thru-hull valves squirt a bit when the valve is opened or closed.  At this point, it doesn't make sense to replace any of them...they aren't very accessible so that is a good thing.
View into the centerboard well showing the 5200 bead at the top making a good seal.
We're getting close to getting Owl Moon back in the water now!

Wednesday, August 24, 2016

The keel has been reattached

August 25, 2016  The boatyard cleaned and prepped the hull and keel Monday and I drove down early Tuesday morning to be there for the reattachment process.
Cleaned hull and keel surfaces ready for bonding.
New centerboard pennant attached

Once the keel bolts were started in the holes of the keel stub, James coated both surfaces with 3M 5200 marine sealant.

All surfaces coated and ready for bonding
The holes at the bottom of the keel where counter sunk so that the sealant could form a good seal there.  The base of each keel bolt got a good extra ring of sealant to fill the counter sink space.  The keel bolts were also smeared up about 2 inches with 5200...I didn't get a photo of that final step.
A lot of sealant squished out when the hull was lowered onto the keel.  That was expected...better too much sealant than not enough.
Now it was time to go inside and put the new washers and nuts on the keel bolts.  James and Ken put 5200 on the base of the keel bolts above the backing plates to help lock the nuts in place.  Then the nuts were tightened a little at a time, working from the center out.  The 1/2" bolts went to 45 ft. lbs., the 3/4" bolts went to 131 ft. lbs. and the 1" bolts went to 300 ft. lbs.
It took a big torque wrench to get the 300 ft lbs. on the two 1" bolts.
Here are all 20 nuts in place.
 18 of the 20 nuts in place
Two are out of sight of the camera...the forward most one under the mast step and the aft most one under a floor section.
James did a good job cleaning the keel/hull joint.

Sunday, August 21, 2016

Hull is lowered back onto the keel

August 18, 2016  With the top of the keel, keel bolts and bottom of the keel stub taped, the hull was lowered on to the keel Thursday.  This is so that the backing plates of 3/4" G10 material that James had prepared could be set in place with epoxy. The G10 material has a compression load tolerance of 60,000 psi.
Taped keel
Taped keel stub
Moving Owl Moon into position over the keel.

Holes in the keel stub lined up with the keel bolts...took a bit of fine maneuvering with the travel lift.

Backing plates all lined up ready for installation.  Not the number key for each one.
Setting the backing plates with epoxy...the aft set (bottom of photo) have been completed.

Saturday, August 13, 2016

Checking In on Owl Moon

August 9, 2016 After returning from Maine following an enjoyable time on the Annual Corinthians Cruise where we missed having Owl Moon, I drove down to Regent Point to check in on Owl Moon.  We have received the go ahead from Jim Taylor that reattaching the keel can be done and the yard has been taking some steps in preparation for that.
The yard created a stand in for the keel stub, matching the holes.  This created a flat surface for using to create a flatter surface on the top of the keel by using epoxy between the board and the keel.
Difficult to see in these photos, but the "board on keel" process left some rough spots that need sanding.

The latter part of this week they are cutting and fitting backing plates out of G10 (material made from fiberglass and epoxy) for each keel bolt nut.

The plastic thru hull fitting for the forward AC unit outflow that St. Augustine Marine installed earlier this year when they raised the location above the waterline has been replaced with a stainless steel fitting that does not have an elbow. 

Aft thru hull for AC outflow has been raised above the waterline.
Owl Moon on blocks in the shed without the keel

 5" duct has been run off the aft 16,000 BTU AC unit into a cut out above the nav station.  This will allow the unit to push more air and run more efficiently.
Cutout for grill above nav station.  This will deliver cool air to the main salon.
On the next visit, the new grill had been installed

A pair of rope clutches have been installed for the jib furling lines to replace the jam cleats that were difficult to use.  These will be easier to use and take some load off the stantion base where the jam cleats had been.
 Communications cable for the wind instrument has been protected and secured appropriately at the top of the mast, wiring harness reinstalled with the new VHF cable and the opening at the top of the mast closed off with a piece of fiberglass...no more birds nesting there!
New Aqua Signal LED Tricolor installed at the top of the mast.